211 Jefferson St
San Francisco permit 202510217812 · North Beach
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
1/f -to include the construction of non bearing partitions that was graphically shown on permitted drawings but not detailed theirin. to perform mech and elec work in this adjacent tenant space (art gallery) necessitated by the previously permitted work.
- Filed
- Oct 21, 2025
- Issued
- Jan 2, 2026 (2 months after filing)
- Completed
- Oct 28, 2026 (10 months after issuance)
- Review stops
- 21 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 21, 2025 | Oct 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 21, 2025 | Oct 21, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 22, 2025 | Oct 22, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2025 | Oct 22, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 22, 2025 | Oct 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2025 | Oct 22, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Nov 12, 2025 | Nov 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 12, 2025 | Nov 12, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Nov 12, 2025 | Nov 12, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Nov 13, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 13, 2025 | Nov 13, 2025 | Approved |
Intake Building Inspection · INTAKE | Nov 25, 2025 | Nov 25, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2025 | Nov 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Nov 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 25, 2025 | Nov 25, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 25, 2025 | Nov 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 25, 2025 | Nov 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2025 | Nov 25, 2025 | Approved |
Address verification Building Inspection · ADDR | Dec 1, 2025 | Dec 1, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2025 | Jan 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Steven Liederman | Architect | C29534 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026