2713 Sutter St
San Francisco permit 202510248097 · Presidio Heights
Add a dwelling unit on 1/f under zoning density, provide 1hr fire rated wall and ceiling.
- Filed
- Nov 6, 2025
- Issued
- Feb 2, 2026 (3 months after filing)
- Completed
- May 19, 2026 (3 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 23, 2025 | Nov 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2025 | Nov 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 7, 2025 | Nov 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2025 | Dec 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2025 | Nov 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 7, 2025 | Nov 10, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2025 | Nov 19, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 7, 2025 | Nov 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2025 | Nov 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 7, 2025 | Jan 26, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Dec 8, 2025 | Dec 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 5, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2026 | Jan 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2026 | Jan 14, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 6, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Jan 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 22, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Jan 23, 2026 | Jan 26, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2026 | Feb 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $184,105
| Name | Role | License on permit |
|---|---|---|
| Dawn Ma Q Architecture | Architect | C64315 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022