1304 Valencia St
San Francisco permit 202510248098 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Structural revision to pa# 202204202645-s1, replace an existing unreinforced masonry foundation in poor condition along property line with poured reinforced concrete foundation. add 1-bathroom with 1-sink and 1-toilet within (e) floor plan on 3rd floor.
- Filed
- Mar 13, 2026
- Issued
- May 1, 2026 (2 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 24, 2025 | Oct 24, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 20, 2025 | Nov 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Feb 12, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2026 | Mar 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2026 | Mar 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 13, 2026 | Mar 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 13, 2026 | Mar 18, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Apr 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 13, 2026 | Apr 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2026 | Mar 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 13, 2026 | Apr 23, 2026 | Administrative |
Public health review Public Health · HEALTH | Mar 16, 2026 | Mar 16, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Mar 16, 2026 | Mar 31, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 27, 2026 | Mar 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2026 | Apr 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2026 | Apr 14, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2026 | Apr 14, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2026 | May 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $13,201
| Name | Role | License on permit |
|---|---|---|
| Andrew Bruce Morrall Andrew Morrall Architect | Architect | C26696 |
| Lisa Wai Sum Tse Integrand, Inc | Engineer | S4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026