40 Fanning Wy
San Francisco permit 202510278208 · Inner Sunset
1 story horizontal rear yard addition interior remodel of the existing 1st floor level and basement level
- Filed
- Nov 5, 2025
- Issued
- Mar 10, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 20, 2025 | Nov 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2025 | Nov 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 5, 2025 | Nov 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 5, 2025 | Dec 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 5, 2025 | Dec 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2025 | Nov 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 5, 2025 | Nov 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2025 | Nov 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2025 | Nov 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 5, 2025 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 16, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Feb 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 16, 2026 | Jan 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2026 | Jan 29, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 16, 2026 | Jan 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2026 | Jan 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2026 | Jan 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 18, 2026 | Feb 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Feb 19, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2026 | Feb 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2026 | Mar 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 26, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 18, 2026 | Feb 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2026 | Feb 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $588,145
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Alfred Eade Jeffrey A. Eade Architect | Architect | C-30594 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023