39 Sussex St
San Francisco permit 202510278213 · Glen Park
Add 2 (n) roof dormers on 3rd flr; interior remodel throughout all flrs; relocate kitchen and 2 (e) bathrooms; add a (n) powder room on 2nd flr; add a wet bar on 1st flr; create (n) interior connections between all 3 flrs; build a (n) rear deck on 1st flr.
- Filed
- Jan 13, 2026
- Issued
- Jun 25, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 27, 2025 | Oct 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 27, 2025 | Oct 27, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2025 | Jan 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 14, 2026 | Jan 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 14, 2026 | Mar 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 14, 2026 | Mar 10, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Feb 12, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 14, 2026 | Jan 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2026 | Feb 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 14, 2026 | Jun 18, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 1, 2026 | Apr 1, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 8, 2026 | May 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2026 | May 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 8, 2026 | May 11, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2026 | May 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 2, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2026 | Jun 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2026 | Jun 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2026 | Jun 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 17, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2026 | Jun 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $368,000
| Name | Role | License on permit |
|---|---|---|
| Pak-Yat Lee Sedes Architecture | Architect | C30921 |
| Stephen Chan Tensar Group Inc. | Engineer | 4533 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025