Home remodel (type unconfirmed)Full plan reviewIssued
Street view · Mar 2025
Google Street View of 39 Sussex St, Mar 2025
Scope of work
As written on the permit application.

Add 2 (n) roof dormers on 3rd flr; interior remodel throughout all flrs; relocate kitchen and 2 (e) bathrooms; add a (n) powder room on 2nd flr; add a wet bar on 1st flr; create (n) interior connections between all 3 flrs; build a (n) rear deck on 1st flr.

Timeline
Key dates from the city record.
Filed
Jan 13, 2026
Issued
Jun 25, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
4 times, by Building Inspection, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 27, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 27, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Jan 9, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 14, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 23, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 16, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 10, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Feb 12, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 21, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 3, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jun 18, 2026Administrative

Fire prevention review

Fire Department · SFFD

Apr 1, 2026Approved

Zoning review

Planning · CP-ZOC

May 14, 2026Approved

Building plan review

Building Inspection · BLDG

May 15, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 11, 2026Approved

Fire prevention review

Fire Department · SFFD

May 11, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 20, 2026Approved

Zoning review

Planning · CP-ZOC

Jun 4, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 18, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 5, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 5, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 8, 2026Approved

Zoning review

Planning · CP-ZOC

Jun 10, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 9, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 25, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$368,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Pak-Yat Lee

Sedes Architecture

ArchitectC30921
Stephen Chan

Tensar Group Inc.

Engineer4533
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202510278213 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record