1282 Sacramento St #0
San Francisco permit 202510288306 · Nob Hill
Private roof deck, remodel of kitchen, new powder room, new penthouse roof & skylights, structural work.
- Filed
- Jan 6, 2026
- Issued
- May 22, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 27, 2025 | Nov 14, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 14, 2025 | Dec 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2025 | Jan 7, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2026 | Jan 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 7, 2026 | Feb 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 7, 2026 | Feb 27, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2026 | Jan 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 7, 2026 | Apr 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2026 | Jan 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2026 | Jan 14, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 7, 2026 | May 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 30, 2026 | Mar 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 31, 2026 | Mar 31, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2026 | Apr 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2026 | Apr 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 21, 2026 | Apr 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2026 | May 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2026 | May 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 7, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2026 | May 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 8, 2026 | May 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 8, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2026 | May 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 12, 2026 | May 22, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $125,000
| Name | Role | License on permit |
|---|---|---|
| David George Yama Yama Architecture | Architect | C32627 |
| Austin Payne Upright Engineering | Engineer | C71212 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026