230 04th Av
San Francisco permit 202510298356 · Inner Richmond
Legalization of illegal unit as approved under #2017-011948prj, remodel of kitchen and bathroom at new adu, unit 3-2/f. replace wood stairs at rear of building. upgrade electrical panel for adu to 100amp panel. install new street tree in sidewalk. state adu program.
- Filed
- Feb 11, 2026
- Issued
- Oct 30, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 33 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 27, 2025 | Nov 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2025 | Feb 11, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Feb 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2026 | Feb 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 11, 2026 | Feb 18, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2026 | Feb 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 11, 2026 | Mar 3, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2026 | Feb 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 11, 2026 | May 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2026 | Apr 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2026 | Mar 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2026 | Apr 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2026 | Mar 30, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 20, 2026 | Mar 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2026 | Mar 23, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 20, 2026 | Apr 7, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2026 | Mar 26, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 31, 2026 | Mar 31, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 27, 2026 | May 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | May 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 27, 2026 | May 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 27, 2026 | May 8, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Apr 27, 2026 | May 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 27, 2026 | Apr 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 27, 2026 | May 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2026 | May 6, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 12, 2026 | May 12, 2026 | Administrative |
Address verification Building Inspection · ADDR | May 14, 2026 | May 14, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 14, 2026 | Oct 30, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2026 | Oct 29, 2026 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Oct 30, 2026 | Oct 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $104,865
| Name | Role | License on permit |
|---|---|---|
| Stephanie Mary Wong Swigspace | Architect | C31739 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026