3215 Broderick St
San Francisco permit 202510308568 · Marina
Vertical addition. renovation & expansion of (e) 2 units. add level 4, set back from front & rear. reduction of north lightwell. reduce footprint of garage. expand lower unit down into rear garage level (level 1). expand upper unit up to new level 4.
- Filed
- Dec 29, 2025
- Issued
- Jun 23, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 29, 2025 | Nov 14, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2025 | Dec 30, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 9, 2025 | Dec 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 30, 2025 | May 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 30, 2025 | Feb 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 30, 2025 | Feb 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2025 | Jan 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 30, 2025 | Jan 12, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 30, 2025 | Jan 6, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 30, 2025 | Jan 31, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2025 | Jan 6, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 30, 2025 | Jun 5, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 2, 2026 | Apr 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2026 | Apr 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 2, 2026 | Apr 9, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2026 | Apr 13, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 2, 2026 | May 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2026 | Apr 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 5, 2026 | May 12, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 5, 2026 | May 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2026 | May 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 5, 2026 | May 14, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 5, 2026 | May 7, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2026 | May 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2026 | May 22, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 21, 2026 | May 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 22, 2026 | Jun 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 22, 2026 | May 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 22, 2026 | May 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 22, 2026 | Jun 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 22, 2026 | Jun 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2026 | May 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2026 | Jun 23, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,238,704
| Name | Role | License on permit |
|---|---|---|
| Hallie Chen Caha Design Group | Authorized agent-others | C38753 |
| Casey Burdett Ramirez Caha Design Group | Architect | C40159 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025