129 12th Av
San Francisco permit 202511038737 · Inner Richmond
To comply with nov #202542181. remove 3 columns and a beam installed under existing front baywindows w/o a permit on g/f
- Filed
- Nov 3, 2025
- Issued
- Nov 7, 2025 (within 1 month of filing)
- Completed
- May 5, 2026 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 5 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Nov 3, 2025 | Nov 3, 2025 | Approved |
Intake Building Inspection · INTAKE | Nov 3, 2025 | Nov 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 3, 2025 | Nov 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Nov 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2025 | Nov 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $5,000
| Name | Role | License on permit |
|---|---|---|
| Michael Chan Michael Chan Company | Engineer | C72969 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019