1239 Geneva Av #0
San Francisco permit 202511038738 · Excelsior
To comply with nov # 202536212 commercial: r/r damaged drywall, insulation and electrical. hallways & stairways: r/r damaged drywall and insulation. unit 2: r/r damaged wall framing, windows, doors, drywall, inulation, test (e) electrical and plumbing.
- Filed
- Nov 24, 2025
- Issued
- Aug 6, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2025 | Nov 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 10, 2025 | Dec 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 10, 2025 | Jan 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 10, 2025 | Jan 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 10, 2025 | Jan 5, 2026 | Not Applicable |
Public health food review Public Health · HEALTH-FD | Dec 10, 2025 | Dec 11, 2025 | Not Applicable |
Public Health HEALTH-MB | Dec 10, 2025 | Dec 11, 2025 | Not Applicable |
Building inspector Building Inspection · BID-INSP | Dec 10, 2025 | Dec 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 10, 2025 | Jul 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 13, 2026 | Mar 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2026 | Apr 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Apr 1, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 31, 2026 | May 4, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 10, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2026 | Jun 15, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 1, 2026 | Jul 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2026 | Jul 17, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2026 | Jul 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2026 | Aug 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Mark Paul Rivera Powell And Associates | Architect | C-66864 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025