Scope of work
As written on the permit application.

Proposed child care facility that includes: conversion of garage into a child play area, convervsion of bedroom 2&3 into 1 big room, conversion of bedroom 1 into an isolation room with lavatory, conversion of entertainment room into indoor art room, conversion of detached storage into outdoor art..

Timeline
Key dates from the city record.
Filed
Apr 8, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 6 departments
Comments issued
14 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 3, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 3, 2025Approved

Permit Center

Permit Center · PERMIT-CTR

Jan 6, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 13, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 10, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 16, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 3, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 26, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 1, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Apr 17, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 14, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 16, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 5, 2026Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Apr 21, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

In progress—

Electrical plan review

Building Inspection · MECH-E

Aug 18, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 24, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 21, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Sep 2, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Sep 3, 2026Not Applicable

Building plan review

Building Inspection · BLDG

Oct 22, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 27, 2026Approved

Fire prevention review

Fire Department · SFFD

Oct 21, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 29, 2026Approved

Zoning review

Planning · CP-ZOC

Oct 30, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 30, 2026Issued Comments

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Fire prevention review

Fire Department · SFFD

In progress—

Street use and mapping

Public Works · DPW-BSM

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$120,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
James Enright

Jt Structural

EngineerS7245
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511038741 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record