20 Franklin St
San Francisco permit 202511038742 · Hayes Valley
Ed13-01 priority: renovation to units of 100% affordable housing: voluntary seismic upgrades, accessibility upgrades, mep upgrades, facade repair, relocation of amenitie4s to g/f from the basement and interior repair.
- Filed
- Dec 18, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 46 stops across 7 departments
- Comments issued
- 16 times, by Permit Center, Building Inspection, Fire Department, Public Utilities, Planning, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2025 | Nov 19, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 28, 2025 | Dec 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2025 | Dec 18, 2025 | Administrative |
Apartment and hotel inspection Building Inspection · HIS | Dec 18, 2025 | Dec 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2025 | Dec 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | Feb 13, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Dec 18, 2025 | Dec 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2025 | Dec 23, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 18, 2025 | Dec 30, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2025 | Dec 29, 2025 | Issued Comments |
Public Health HEALTH-MH | Dec 18, 2025 | Dec 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 18, 2025 | Nov 4, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Feb 12, 2026 | Feb 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 24, 2026 | Apr 29, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 28, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Apr 24, 2026 | May 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 29, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | May 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | May 5, 2026 | Issued Comments |
Public Health HEALTH-MH | Apr 24, 2026 | May 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | Apr 29, 2026 | Approved-Stipulated |
Building plan review quality control Building Inspection · BLDG-QC | May 20, 2026 | May 29, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 22, 2026 | Jun 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 22, 2026 | Jul 1, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 22, 2026 | Jun 29, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2026 | Jun 24, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 22, 2026 | Jul 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 22, 2026 | Jul 6, 2026 | Issued Comments |
Public Health HEALTH-MH | Jun 22, 2026 | Jul 2, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 1, 2026 | Jul 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 24, 2026 | Sep 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 24, 2026 | Sep 29, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Sep 24, 2026 | Sep 28, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2026 | Sep 30, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 24, 2026 | Oct 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 24, 2026 | Sep 29, 2026 | Issued Comments |
Public Health HEALTH-MH | Sep 24, 2026 | Sep 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 16, 2026 | Oct 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2026 | Oct 23, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 16, 2026 | Oct 19, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2026 | Oct 19, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 16, 2026 | Oct 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2026 | Oct 27, 2026 | Issued Comments |
Public Health HEALTH-MH | Oct 16, 2026 | Oct 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 30, 2026 | Nov 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2026 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $30,000,000
| Name | Role | License on permit |
|---|---|---|
| Eric S Robinson Paulett Taggart Architects | Architect | C28139 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025