79 A Everson St
San Francisco permit 202511038758 · Glen Park
Construction of new type v-b, 1 story, 1 basement 820sf adu and installation of 620sf paved courtyard.
- Filed
- Dec 3, 2025
- Issued
- Aug 12, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 8 times, by Planning, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2025 | Nov 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2025 | Dec 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 4, 2025 | Dec 9, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 4, 2025 | Dec 22, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 4, 2025 | Dec 17, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2025 | Dec 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 4, 2025 | Dec 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2025 | Dec 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 4, 2025 | Dec 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2025 | Dec 17, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 4, 2025 | Dec 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 4, 2025 | Jul 27, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2025 | Dec 23, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Dec 22, 2025 | Dec 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2026 | Apr 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2026 | Apr 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2026 | Apr 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2026 | Apr 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2026 | Apr 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 10, 2026 | Apr 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2026 | Apr 20, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 10, 2026 | Apr 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 7, 2026 | Jul 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 7, 2026 | Jul 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 7, 2026 | Jul 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2026 | Jul 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 7, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2026 | Jul 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 7, 2026 | Jul 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2026 | Jul 15, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 7, 2026 | Jul 8, 2026 | Approved |
Address verification Building Inspection · ADDR | Jul 16, 2026 | Jul 27, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Jul 22, 2026 | Jul 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 27, 2026 | Aug 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Michael Lino Garcia Garcia Tamjidi | Architect | C-24690 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022