1120 Athens St
San Francisco permit 202511038779 · Excelsior
Erect 2-story detached type-vb adu in rear of 390 rolph st.
- Filed
- Nov 24, 2025
- Issued
- Jun 5, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 2, 2025 | Nov 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2025 | Nov 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 25, 2025 | Dec 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Dec 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2025 | Dec 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 25, 2025 | Dec 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 25, 2025 | Nov 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2025 | Nov 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 25, 2025 | Dec 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2025 | Dec 4, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 25, 2025 | May 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 9, 2026 | Feb 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2026 | Mar 16, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 9, 2026 | Mar 16, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2026 | Feb 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 9, 2026 | Feb 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2026 | Feb 19, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 9, 2026 | Mar 4, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2026 | Feb 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | Apr 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 1, 2026 | Apr 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2026 | Apr 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2026 | Apr 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 1, 2026 | Apr 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2026 | Apr 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 1, 2026 | May 11, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2026 | Apr 2, 2026 | Approved |
Address verification Building Inspection · ADDR | May 8, 2026 | May 11, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | May 12, 2026 | May 12, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 12, 2026 | Jun 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Adam Michael Franch Adam Franch Architecture | Architect | C34374 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025