San Francisco permit 202511038782 · Excelsior

AdditionFull plan reviewIssued
Street view · Mar 2019
Google Street View of 390 Rolph St, Mar 2019
Scope of work
As written on the permit application.

Lower level (905 sq ft) addition of (e) 2 bedroom 1 bath. addition of 1 bedroom, 1 bathroom total 3 bed 2 bath. 429 sq ft detach adu separate permit. 4 ft high wood fence install along street facing property line.

Timeline
Key dates from the city record.
Filed
Nov 24, 2025
Issued
Jun 5, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
8 times, by Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 19, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 25, 2025Administrative

Zoning review

Planning · CP-ZOC

Dec 1, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 19, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 19, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 10, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 26, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Nov 26, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 19, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 4, 2025Approved

Permit Processing Center

Building Inspection · PPC

May 12, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 9, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 18, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 25, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 10, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Feb 11, 2026Approved

Urban forestry

Public Works · DPW-BUF

Mar 4, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 10, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 2, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 2, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 2, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 9, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 9, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Apr 15, 2026Approved

Urban forestry

Public Works · DPW-BUF

May 11, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 2, 2026Approved

Development fee collection

Building Inspection · DFCU

May 12, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Jun 5, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$600,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Adam Michael Franch

Adam Franch Architecture

ArchitectC34374
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511038782 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record