14 30th St
San Francisco permit 202511058954 · Bernal Heights
Erect rear 2-story type vb detached adu
- Filed
- Nov 5, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 17 stops across 6 departments
- Comments issued
- Twice, by Permit Center
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 4, 2025 | Nov 18, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 26, 2025 | Dec 18, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 18, 2026 | Apr 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2026 | In progress | In Progress |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Public Utilities programs review Public Utilities · SFPUC-PRG | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Building inspector Building Inspection · BID-INSP | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Triage
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Dawn Ma Q-Architecture | Architect | C64315 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019