1025 Ashbury St
San Francisco permit 202511079163 · Haight Ashbury
Garage/basement lvl: excavate vertical & horizontal (e)garage area to create ceiling height & flr area; excavate adjacent crawl space area for (n) habitable areas (office, bathrm, inter stairs,laundry rm); 1/f inter remodel & in-fill (e) light well on south facade; 2/f inter remodel & in-fill (e) l
- Filed
- Nov 26, 2025
- Issued
- Jun 8, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 6, 2025 | Nov 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 26, 2025 | Nov 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 26, 2025 | Dec 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 26, 2025 | Jan 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2025 | Jan 7, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 26, 2025 | Dec 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 26, 2025 | Dec 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2025 | Nov 26, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 26, 2025 | Dec 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 26, 2025 | Dec 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 26, 2025 | Mar 31, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2025 | Dec 15, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 7, 2026 | Jan 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 29, 2026 | Feb 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2026 | Feb 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Feb 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2026 | Feb 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 29, 2026 | Feb 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2026 | Feb 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 29, 2026 | Feb 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2026 | Jan 30, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Feb 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2026 | Feb 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2026 | Feb 17, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 11, 2026 | Mar 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2026 | Feb 25, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2026 | Feb 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 9, 2026 | Mar 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 9, 2026 | Mar 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 9, 2026 | Mar 17, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2026 | Mar 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 9, 2026 | Mar 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 9, 2026 | Mar 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 9, 2026 | Mar 30, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 9, 2026 | Mar 13, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Mar 30, 2026 | Mar 31, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2026 | Jun 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $793,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Alfred Eade Jeffrey A. Eade Architect | Architect | C30594 |
| Alexander Michael Santos Altos Engineering | Engineer | C84144 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024