Deck, stairs or patio cover (type unconfirmed)Over-the-counter, with plansComplete
Street view · Mar 2025
Google Street View of 350 University St, Mar 2025
Scope of work
As written on the permit application.

All work is at 1/f -project is limited to modifications to the north stair egress path & associated modifications to existing components along this path. scope includes slective demolition of non-load bearing partitions, new rated doors and frames, exit lighting, new exterior exit stair & associated

Timeline
Key dates from the city record.
Filed
Nov 7, 2025
Issued
Dec 12, 2025 (1 month after filing)
Completed
Dec 31, 2025 (within 1 month of issuance)

For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
15 stops across 5 departments
Comments issued
4 times, by Planning, Building Inspection
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Nov 7, 2025Administrative

Intake

Building Inspection · INTAKE

Nov 7, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 10, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Nov 13, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Dec 10, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 18, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 1, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 2, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 4, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Dec 8, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 10, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 10, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 11, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 11, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 12, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Complete
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael Joseph Castro

Michael Castro

ArchitectC24073
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511079184 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record