788 A 17th Av
San Francisco permit 202511079227 · Outer Richmond
Legalize udu at (e) garage rear via state adu program. no structural work is planned under this scope of work.
- Filed
- Nov 25, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 6, 2025 | Nov 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 26, 2025 | Nov 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 26, 2025 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 26, 2025 | Dec 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 26, 2025 | Dec 11, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 26, 2025 | Dec 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2025 | Dec 1, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 26, 2025 | Dec 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 26, 2025 | Dec 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 26, 2025 | May 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 22, 2026 | Apr 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Apr 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2026 | Apr 24, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Apr 22, 2026 | Apr 24, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2026 | Apr 27, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 22, 2026 | May 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2026 | Apr 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 30, 2026 | Apr 30, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 7, 2026 | May 7, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 14, 2026 | May 15, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 15, 2026 | In progress | — |
Address verification Building Inspection · ADDR | May 21, 2026 | May 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $157,775
| Name | Role | License on permit |
|---|---|---|
| Steven B Hall Shc Architect | Architect | C28168 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025