CheckMyDesigner

788 A 17th Av

San Francisco permit 202511079227 · Outer Richmond

ADUFull plan reviewApproved
Street view · May 2025
Google Street View of 788 A 17th Av, May 2025
Scope of work
As written on the permit application.

Legalize udu at (e) garage rear via state adu program. no structural work is planned under this scope of work.

Timeline
Key dates from the city record.
Filed
Nov 25, 2025
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
5 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 26, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 15, 2026Approved

Building plan review

Building Inspection · BLDG

Dec 18, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 11, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Dec 2, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 1, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 23, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 5, 2025Approved

Permit Processing Center

Building Inspection · PPC

May 15, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 23, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 28, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 24, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Apr 24, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 27, 2026Approved

Urban forestry

Public Works · DPW-BUF

May 14, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 27, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 30, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

May 7, 2026Approved

Development fee collection

Building Inspection · DFCU

May 15, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

In progress—

Address verification

Building Inspection · ADDR

May 21, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Approved
Estimated cost
$157,775
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Steven B Hall

Shc Architect

ArchitectC28168
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511079227 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record