Addition (type unconfirmed)Full plan reviewReinstated
Street view · Sep 2026
Google Street View of 527 Holly Park Cr, Sep 2026
Scope of work
As written on the permit application.

Add 1-story addition to inclu new office, 2 bathrooms, 2 bedrooms & interior stairs. interior remodel on basement flr mech room & 2nd flr office room. remove driveway & curb cut. vertical 2/f addition above (e) bldg inclu 74 sqft non-complaint w/sec 242(e).2.c.1 & 16sqft beyond 25% setback. legalize

Timeline
Key dates from the city record.
Filed
Dec 31, 2025
Issued
Aug 19, 2026 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 6 departments
Comments issued
9 times, by Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 26, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Dec 30, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 5, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 16, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 18, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 26, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 13, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jan 6, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Feb 3, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 5, 2026Approved

Permit Processing Center

Building Inspection · PPC

Aug 3, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Apr 9, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 16, 2026Issued Comments

Building plan review

Building Inspection · BLDG

May 8, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

May 8, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 5, 2026Approved

Street use and mapping

Public Works · DPW-BSM

May 28, 2026Approved

Zoning review

Planning · CP-ZOC

Jun 9, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 11, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jun 8, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jun 16, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 17, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jul 30, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 19, 2026Administrative

Development fee collection

Building Inspection · DFCU

Aug 18, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Reinstated
Estimated cost
$653,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Dawn Ma

Q Architecture

EngineerC64315
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511139484 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record