527 Holly Park Cr
San Francisco permit 202511139484 · Bernal Heights
Add 1-story addition to inclu new office, 2 bathrooms, 2 bedrooms & interior stairs. interior remodel on basement flr mech room & 2nd flr office room. remove driveway & curb cut. vertical 2/f addition above (e) bldg inclu 74 sqft non-complaint w/sec 242(e).2.c.1 & 16sqft beyond 25% setback. legalize
- Filed
- Dec 31, 2025
- Issued
- Aug 19, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 11, 2025 | Nov 26, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 15, 2025 | Dec 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2025 | Jan 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 5, 2026 | Jan 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 5, 2026 | Feb 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 5, 2026 | Feb 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 5, 2026 | Jan 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 5, 2026 | Jan 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 5, 2026 | Jan 6, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 5, 2026 | Feb 3, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2026 | Jan 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 5, 2026 | Aug 3, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2026 | Apr 9, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | May 4, 2026 | May 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 4, 2026 | May 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2026 | May 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | May 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2026 | Jun 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2026 | Jun 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 5, 2026 | Jun 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2026 | Jun 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 30, 2026 | Jul 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2026 | Aug 19, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Aug 18, 2026 | Aug 18, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $653,000
| Name | Role | License on permit |
|---|---|---|
| Dawn Ma Q Architecture | Engineer | C64315 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026