3175 17th St
San Francisco permit 202511179769 · Mission
Change of use of an existing 14,320 sf, builing with an 5,684 sf addition of dance studios and support spaces. a new 3rd level performance space and a 1,508 sf rooftop terrace (590 sf occupiable). scope includes limited improvements at 3153 17th st as well as interconnections between 2 buildings.
- Filed
- Dec 9, 2025
- Issued
- Jul 24, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 68 stops across 7 departments
- Comments issued
- 22 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Permit Center, Public Health
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 14, 2025 | Dec 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2025 | Dec 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 10, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 10, 2025 | Jan 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 10, 2025 | Jan 30, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2025 | Dec 11, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 10, 2025 | Jan 11, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2025 | Dec 19, 2025 | Issued Comments |
Public Health HEALTH-MH | Dec 10, 2025 | Dec 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 10, 2025 | Jul 17, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 5, 2026 | Jan 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 28, 2026 | Jan 28, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 28, 2026 | Jan 28, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2026 | Mar 27, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 2, 2026 | Apr 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 28, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | May 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 2, 2026 | Apr 14, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2026 | Apr 13, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Apr 2, 2026 | May 11, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 6, 2026 | Approved |
Public Health HEALTH-MH | Apr 2, 2026 | Apr 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 23, 2026 | Apr 23, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Apr 29, 2026 | Jul 8, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 21, 2026 | May 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 23, 2026 | Jul 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2026 | Jun 26, 2026 | Approved |
Public Health HEALTH-MH | Jun 24, 2026 | Jul 2, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 26, 2026 | Jun 26, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2026 | Jul 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2026 | Jul 2, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2026 | Jul 13, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 13, 2026 | Jul 16, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2026 | Jul 24, 2026 | Administrative |
Addendum 1: Demo foundations & superstructure (core shell)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2026 | Aug 14, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2026 | Sep 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 9, 2026 | Sep 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 9, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Oct 16, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2026 | Sep 15, 2026 | Issued Comments |
Public Health HEALTH-MH | Sep 9, 2026 | Sep 10, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 9, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2026 | Oct 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2026 | Oct 14, 2026 | Approved |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Architecture/mep/t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2026 | Aug 14, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Sep 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 9, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2026 | Oct 9, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2026 | Oct 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Oct 7, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2026 | Oct 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 9, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2026 | Sep 10, 2026 | Approved |
Public Health HEALTH-MH | Sep 9, 2026 | Sep 22, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 9, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Oct 1, 2026 | Oct 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $7,273,634
| Name | Role | License on permit |
|---|---|---|
| Peter Wright Pfau Perkins & Will | Architect | C21794 |
| Michael Paul Gemmill Nabih Youssef | Engineer | S-4703 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023