30 Commonwealth Av
San Francisco permit 202511189828 · Presidio Heights
Interior remodel & rear yard addition of (e) single family home includes structural & shoring work.
- Filed
- Dec 10, 2025
- Issued
- Jun 11, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 17, 2025 | Dec 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2025 | Dec 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 11, 2025 | Jan 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2025 | Jan 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2025 | Jan 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 11, 2025 | Dec 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2025 | Dec 18, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 11, 2025 | Jan 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2025 | Dec 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 11, 2025 | May 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 23, 2026 | Mar 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 23, 2026 | Mar 25, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 23, 2026 | Mar 25, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2026 | Mar 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 23, 2026 | Apr 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2026 | Apr 1, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 23, 2026 | Apr 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 23, 2026 | Mar 26, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 24, 2026 | Apr 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2026 | May 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2026 | May 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | Apr 28, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 29, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | May 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 28, 2026 | Apr 29, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 13, 2026 | May 14, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 18, 2026 | May 28, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 28, 2026 | Jun 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $988,000
| Name | Role | License on permit |
|---|---|---|
| Stephen Sedgwick Sutro Sutro Architects | Architect | C30702 |
| Denny Chi-Ho Kwan Holmes-Culley | Engineer | S4887 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2024