Revision to pa 202305177995 layout changes to 1st fl layount; 2nd fl layout & 3rd floor layout; new interior stair; reduced scope @ 3rd fl & roof; reduced horizontal addition - more existing roof line to remain
- Filed
- Dec 18, 2025
- Issued
- May 28, 2026 (5 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 18, 2025 | Nov 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 18, 2025 | Nov 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2025 | Nov 21, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 26, 2025 | Dec 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2025 | Dec 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2025 | Apr 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2025 | Feb 6, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2025 | Dec 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2025 | Jan 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2025 | Dec 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2025 | Dec 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 19, 2025 | May 7, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Feb 6, 2026 | Feb 6, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 23, 2026 | Mar 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | Apr 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2026 | Apr 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 20, 2026 | Apr 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 22, 2026 | Apr 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | May 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 7, 2026 | May 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Glenda Flaim Butler Armsden Architects | Architect | C-32433 |
| Randy Edward Collins Ftf Engineering, Inc | Engineer | S4802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025