CheckMyDesigner

1030 Francisco St

San Francisco permit 202511199960 · Russian Hill

New buildingFull plan reviewIssued
Street view · Feb 2017
Google Street View of 1030 Francisco St, Feb 2017
Scope of work
As written on the permit application.

To erect 3 stories, type v, no basement, single family residence and attached adu.

Timeline
Key dates from the city record.
Filed
Dec 14, 2025
Issued
May 13, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
7 times, by Building Inspection, Public Works, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 15, 2025Administrative

Zoning review

Planning · CP-ZOC

Apr 13, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 22, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 14, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 29, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 18, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 23, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jan 12, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 22, 2025Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Dec 31, 2025Approved

Permit Processing Center

Building Inspection · PPC

Apr 29, 2026Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Jan 21, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Feb 24, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 25, 2026Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Feb 25, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 26, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Mar 25, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Mar 18, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 20, 2026Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Apr 17, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 17, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 18, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 24, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 31, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 29, 2026Approved

Development fee collection

Building Inspection · DFCU

Apr 14, 2026Administrative

Address verification

Building Inspection · ADDR

Apr 28, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 13, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$3,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David M Strandberg

Strandberg Engineering

Engineer62993
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511199960 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record