2578 Great Hy
San Francisco permit 202511240327 · Sunset/Parkside
Remodel of (e) 3 story single family residence. horizontal addition on 3 levels in rear. add one bedroom local program adu on 1st floor. vertical extension with new siding & windows throughout.
- Filed
- Dec 11, 2025
- Issued
- Feb 18, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 20, 2025 | Dec 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 24, 2025 | Dec 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 12, 2025 | Dec 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 12, 2025 | Jan 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 12, 2025 | Jan 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2025 | Dec 30, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Dec 12, 2025 | Dec 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2025 | Dec 16, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 12, 2025 | Jan 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2025 | Dec 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 12, 2025 | Feb 9, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2026 | Jan 12, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 13, 2026 | Jan 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 26, 2026 | Jan 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 26, 2026 | Feb 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 26, 2026 | Feb 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2026 | Feb 3, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 26, 2026 | Jan 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2026 | Jan 28, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 26, 2026 | Feb 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2026 | Jan 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2026 | Feb 3, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 9, 2026 | Feb 9, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2026 | Feb 18, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $740,841
| Name | Role | License on permit |
|---|---|---|
| Jeffrey B E Logan Lapnog Architecture | Architect | C22634 |
| Shaun Edward Moynahan Semco Engineering, Inc. | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022