1906 Folsom St
San Francisco permit 202511250455 · Mission
Convert g/f vacant storage to 3 new adu per ord#162-16. replace wood framed stair at rear yard in kind. coordinate work w/ soft story #202501305531. infill light wells at g/f & rear expansion at g/f.
- Filed
- Jan 21, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 43 stops across 7 departments
- Comments issued
- 15 times, by Permit Center, Planning, Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 21, 2025 | Dec 11, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 23, 2025 | Jan 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 16, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Apr 20, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Jan 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Feb 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Feb 24, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Feb 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 28, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 21, 2026 | Feb 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 28, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | Nov 3, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 22, 2026 | Jan 31, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 30, 2026 | Jan 30, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 10, 2026 | Mar 10, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 10, 2026 | Mar 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 14, 2026 | Apr 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 14, 2026 | May 7, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 20, 2026 | May 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 20, 2026 | Apr 20, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 23, 2026 | Apr 23, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 24, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 6, 2026 | May 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 1, 2026 | Jun 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2026 | Jun 18, 2026 | Approved |
Public Health HEALTH-MH | Jun 26, 2026 | Jun 26, 2026 | Approved |
Public Health HEALTH-MH | Aug 4, 2026 | Aug 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2026 | Aug 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2026 | Sep 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Aug 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2026 | Aug 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Aug 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2026 | Aug 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2026 | Aug 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 19, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 27, 2026 | Aug 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Sep 21, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 18, 2026 | Sep 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 21, 2026 | Sep 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 29, 2026 | Oct 27, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Oct 28, 2026 | Nov 3, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 3, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Serina L Calhoun Syncopated Architecture | Architect | C-30744 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025