San Francisco permit 202511250462 · Potrero Hill

Commercial or tenant improvementFull plan reviewIssued
Scope of work
As written on the permit application.

Priority project(block 9)potrero power station development agreement.scope includes partial demolition of interior concrete floor and partial demolition of concrete header above existing door. structural retrofit including new foundation piles, a new mat slab and a new interior reinforcement wall.

Timeline
Key dates from the city record.
Filed
Dec 19, 2025
Issued
Jun 25, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 5 departments
Comments issued
12 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 11, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 19, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 12, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 21, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 21, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 2, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Feb 11, 2026Issued Comments

Public Health

HEALTH-MH

Dec 31, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jun 4, 2026Administrative

Building plan review

Building Inspection · BLDG

Apr 3, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Apr 3, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Apr 8, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Apr 8, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Apr 27, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 27, 2026Issued Comments

Zoning review

Planning · CP-ZOC

May 14, 2026Approved

Building plan review

Building Inspection · BLDG

May 15, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

May 15, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 14, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

May 18, 2026Issued Comments

Public Health

HEALTH-MH

May 14, 2026Approved

Zoning review

Planning · CP-ZOC

May 21, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 2, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 2, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 4, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

May 23, 2026Issued Comments

Public Health

HEALTH-MH

May 21, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

May 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 25, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Paul Anthony Littler

Holmes Structural

EngineerS6189
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511250462 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record