61 Coleridge St
San Francisco permit 202511260487 · Bernal Heights
Legalize previously unpermitted merger of two-unit dwelling to comply with nov 202314745 & planning enforcement case#2023-010520enf.areas of work include front door,bath,& interior wall & door changes. provide new bath & laundry renovation.all work occurs within the(e)footprint.
- Filed
- Jan 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 24, 2025 | Dec 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2025 | Jan 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 8, 2026 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Feb 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 8, 2026 | Feb 13, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2026 | Jan 26, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 8, 2026 | Jan 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2026 | Jan 12, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 8, 2026 | Feb 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Feb 4, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 8, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Sep 17, 2026 | Oct 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 17, 2026 | Sep 24, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2026 | Sep 18, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 17, 2026 | Sep 21, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2026 | Sep 24, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 17, 2026 | Oct 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2026 | Sep 25, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $61,611
| Name | Role | License on permit |
|---|---|---|
| Susanna Douglas Susanna Douglas Architecture | Payor | C35117 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022