44 Sheridan St
San Francisco permit 202511260509 · South of Market
Revision or supplementOver-the-counter, with plansComplete
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Scope of work
As written on the permit application.
Revision to pa # 2025-1030-8515: install new 4 x 12 psl beam & specd hardware for attachment
Timeline
Key dates from the city record.
- Filed
- Nov 26, 2025
- Issued
- Nov 26, 2025 (within 1 month of filing)
- Completed
- Jul 13, 2026 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 3 stops across 1 department
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 26, 2025 | Nov 26, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 26, 2025 | Nov 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 26, 2025 | Nov 26, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Eric Lee Cox Kembcon Corp. | Engineer | 3633 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511260509 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026