581 Belvedere St
San Francisco permit 202511260564 · Haight Ashbury
1st floor / basement:convert (e)rooms to adu per state adu program (gov't code 66323): adu sq. ft. if 656 total (180 of that is new); new 37 sq. ft. deck at rear yard for ladder pathway.1st flr voluntary lateral strengthening. no work on 2nd & 3rd floors (e)building not sprinklered & does not have a
- Filed
- Dec 16, 2025
- Issued
- Mar 4, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 25, 2025 | Dec 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2025 | Dec 16, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 16, 2025 | Feb 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Dec 17, 2025 | Dec 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Dec 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 17, 2025 | Jan 6, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2025 | Jan 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 17, 2025 | Dec 22, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 17, 2025 | Dec 22, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 17, 2025 | Jan 6, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2025 | Dec 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 26, 2025 | Jan 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 26, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 26, 2026 | Jan 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 26, 2026 | Feb 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2026 | Feb 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 26, 2026 | Jan 28, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2026 | Jan 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 26, 2026 | Feb 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2026 | Jan 30, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 10, 2026 | Feb 10, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2026 | Mar 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $122,234
| Name | Role | License on permit |
|---|---|---|
| Cassandra Mettling-Davis Cmd Architecture | Architect | C24981 |
| William Ashley Harrison William Harrison Consulting | Engineer | C52343 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025