581 Belvedere St

San Francisco permit 202511260564 · Haight Ashbury

ADUFull plan reviewIssued
Street view · May 2025
Google Street View of 581 Belvedere St, May 2025
Scope of work
As written on the permit application.

1st floor / basement:convert (e)rooms to adu per state adu program (gov't code 66323): adu sq. ft. if 656 total (180 of that is new); new 37 sq. ft. deck at rear yard for ladder pathway.1st flr voluntary lateral strengthening. no work on 2nd & 3rd floors (e)building not sprinklered & does not have a

Timeline
Key dates from the city record.
Filed
Dec 16, 2025
Issued
Mar 4, 2026 (3 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
4 times, by Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 16, 2025Administrative

Permit Processing Center

Building Inspection · PPC

Feb 10, 2026Administrative

Zoning review

Planning · CP-ZOC

Dec 22, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 30, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 6, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 2, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 22, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Dec 22, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jan 6, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 22, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 5, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 5, 2026Approved

Building plan review

Building Inspection · BLDG

Jan 30, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 5, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 4, 2026Approved

Fire prevention review

Fire Department · SFFD

Jan 28, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jan 29, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 10, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 30, 2026Approved

Development fee collection

Building Inspection · DFCU

Feb 10, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Mar 4, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$122,234
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Cassandra Mettling-Davis

Cmd Architecture

ArchitectC24981
William Ashley Harrison

William Harrison Consulting

EngineerC52343
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202511260564 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record