360 05th St
San Francisco permit 202512010589 · South of Market
Erect type 1a over 4a 21-story 272 unit residential/commerical building.
- Filed
- Feb 10, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 7 departments
- Comments issued
- 11 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 25, 2025 | Dec 16, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 7, 2026 | Jan 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2026 | Feb 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | May 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Mar 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 10, 2026 | Mar 17, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 19, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Mar 9, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 10, 2026 | Feb 24, 2026 | Issued Comments |
Public Health HEALTH-HM | Feb 10, 2026 | Feb 10, 2026 | Approved |
Public Health HEALTH-AW | Feb 10, 2026 | Feb 25, 2026 | Administrative |
Public Health HEALTH-MH | Feb 10, 2026 | Feb 10, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 10, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2026 | Oct 9, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 17, 2026 | Mar 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2026 | Apr 16, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 16, 2026 | Apr 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | Jun 26, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 5, 2026 | Oct 20, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 8, 2026 | Oct 9, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Address verification Building Inspection · ADDR | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $94,882,000
| Name | Role | License on permit |
|---|---|---|
| Glenn G Rescalvo Handci Architects | Architect | C27080 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023