457 Roosevelt Wy
San Francisco permit 202512020757 · Castro/Upper Market
Legalization of changes pa 201708165047: subbasement addition.(p)subbasement:(p)office & gym.basement:(as-built) 1 bed,1 media rm,rear deck,(p)office.1/f:(as-built) gate & fene at front.(p) trash enclosure under (e) front stair.2/f:(as-built) living rm.ext (as-built) site stair connect yard to bsmt.
- Filed
- Jan 5, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 30, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 5, 2026 | Jan 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 5, 2026 | Feb 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 5, 2026 | Feb 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 5, 2026 | Feb 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 5, 2026 | Jan 30, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 5, 2026 | Jan 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2026 | Jan 12, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 5, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Feb 13, 2026 | Feb 13, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 13, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Jul 1, 2026 | Jul 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2026 | Jul 7, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2026 | Jul 15, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 1, 2026 | Jul 6, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2026 | Jul 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2026 | Sep 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 20, 2026 | Sep 29, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2026 | Sep 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Sven Erik Lavine Sven Lavine Architecture | Architect | C30122 |
| Sean Thomas Condry Stc Design & Engineering | Engineer | C60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025