320 14th St
San Francisco permit 202512040944 · Mission
Legalization of 2 units: 320 & 324, through the adu program (sfpc 207.1).
- Filed
- Jan 29, 2026
- Issued
- Jul 2, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 4 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 2, 2025 | Dec 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2026 | Jan 29, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 29, 2026 | Feb 3, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 29, 2026 | Mar 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Mar 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2026 | Feb 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 29, 2026 | Feb 6, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2026 | Feb 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 29, 2026 | Mar 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2026 | Feb 11, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 29, 2026 | Apr 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 13, 2026 | Mar 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 17, 2026 | Mar 17, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2026 | Mar 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2026 | Mar 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 30, 2026 | Apr 21, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2026 | Apr 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2026 | Apr 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 8, 2026 | Apr 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 9, 2026 | Apr 9, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2026 | Jul 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $284,000
| Name | Role | License on permit |
|---|---|---|
| Mark Kevin Hogan Openscope Studio | Architect | C-33268 |
| Ryan Bogart Zfa Structural Engineers | Engineer | 6104 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026