1123 Sutter St
San Francisco permit 202512040964 · Nob Hill
Permit for temporary tower crane erection for new construction high-rise building
- Filed
- Dec 19, 2025
- Issued
- Jan 29, 2026 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 17 stops across 6 departments
- Comments issued
- 3 times, by CON, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 2, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2025 | Dec 19, 2025 | Administrative |
CON CON-BOND | Dec 19, 2025 | Dec 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 19, 2025 | Jan 13, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2025 | Jan 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 19, 2025 | Jan 9, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2025 | Dec 29, 2025 | Approved |
Public Health HEALTH-HM | Dec 19, 2025 | Dec 22, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Dec 19, 2025 | Jan 28, 2026 | Administrative |
CON CON-BOND | Jan 8, 2026 | Jan 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2026 | Jan 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 15, 2026 | Jan 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 16, 2026 | Jan 16, 2026 | Not Applicable |
Public Health HEALTH-HM | Jan 16, 2026 | Jan 16, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2026 | Jan 28, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Jan 28, 2026 | Jan 28, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2026 | Jan 29, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Joe Gulden Imeg Consulting & Structural | Engineer | 5797 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026