1241 Delaware St
San Francisco permit 202512051066 · Potrero Hill
Mayor dir ed13-01: unit 3-prequel park- potrero power station dev- temp park use & back of house maintenance space(not occupiable to public), under footprint of unit 3 structure. (n)pathways, railings, paving & lighting (deferred). misc, structural work for back on house raised platform on mat slab.
- Filed
- Jul 1, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 7 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 4, 2025 | Dec 19, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 15, 2026 | Jun 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 30, 2026 | Jul 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 6, 2026 | Aug 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 6, 2026 | Aug 7, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 6, 2026 | Aug 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 6, 2026 | Jul 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2026 | Jul 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 6, 2026 | Aug 11, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2026 | Jul 17, 2026 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 6, 2026 | Jul 31, 2026 | Approved |
Public Health HEALTH-MH | Jul 6, 2026 | Jul 31, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 6, 2026 | Sep 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 28, 2026 | Sep 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 28, 2026 | Sep 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2026 | Sep 3, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 28, 2026 | Sep 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2026 | Sep 11, 2026 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 28, 2026 | Sep 9, 2026 | Approved |
Public Health HEALTH-MH | Aug 28, 2026 | Sep 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2026 | Sep 4, 2026 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Paul Anthony Littler Holmes Structural | Engineer | S6189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026