201 Buena Vista East Av
San Francisco permit 202512051105 · Castro/Upper Market
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Permit amendment to bpa #202401043396 to include the renovation to first-floor unit with structural improvements, and modifications to the terrace, courtyard, and yard.
- Filed
- Dec 29, 2025
- Issued
- May 4, 2026 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 2, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2025 | Dec 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 29, 2025 | Jan 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 29, 2025 | Feb 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 29, 2025 | Feb 3, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2025 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Dec 29, 2025 | Jan 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 29, 2025 | Dec 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 29, 2025 | Dec 30, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 29, 2025 | Apr 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 10, 2026 | Mar 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2026 | Apr 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2026 | Mar 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2026 | Mar 16, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2026 | Mar 26, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2026 | Mar 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 27, 2026 | May 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Peter Yen Liang Blue Truck Inc. | Architect | C37831 |
| Randy Edward Collins Ftf Structural Engineering | Engineer | S4802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2021