2234 Market St
San Francisco permit 202512081211 · Castro/Upper Market
Prop h:tenat improvement on existing business space.new interior parttions,finishes & fixtures.new electrical,lighting mechanical systems & controls.new plumbing & fixtures.
- Filed
- Dec 8, 2025
- Issued
- Mar 13, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 32 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 8, 2025 | Dec 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 9, 2025 | Dec 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 9, 2025 | Dec 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2025 | Dec 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 10, 2025 | Dec 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2025 | Dec 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2025 | Dec 16, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 18, 2025 | Dec 18, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2025 | Jan 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2026 | Feb 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Feb 11, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 10, 2026 | Feb 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Feb 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2026 | Feb 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2026 | Feb 17, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 23, 2026 | Feb 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2026 | Feb 23, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 23, 2026 | Feb 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2026 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 24, 2026 | Feb 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2026 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 27, 2026 | Feb 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2026 | Feb 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2026 | Mar 10, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 2, 2026 | Mar 2, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2026 | Mar 5, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 6, 2026 | Mar 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2026 | Mar 12, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 12, 2026 | Mar 12, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2026 | Mar 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,100,000
| Name | Role | License on permit |
|---|---|---|
| Robert Jon Sargenti Sargenti Architects | Architect | C31054 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026