800 Chestnut St
San Francisco permit 202512081243 · Russian Hill
Change use from art college-artist studios. ext facade restoration @ (clay/brown bldg & residential bldg) and accessibility improvements, interior nonstructural improvements and limited new ext openings. repurposing of studio & admin space. add 2 residential dwelling units. seismic under sep permit.
- Filed
- Jan 6, 2026
- Issued
- Sep 4, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 39 stops across 7 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 5, 2025 | Dec 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 6, 2026 | Jan 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 6, 2026 | May 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2026 | Feb 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 6, 2026 | Mar 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2026 | Jan 23, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 6, 2026 | Jan 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 6, 2026 | May 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2026 | Jan 7, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 6, 2026 | Feb 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2026 | Jan 9, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 6, 2026 | Jan 9, 2026 | Approved |
Public Health HEALTH-MH | Jan 6, 2026 | Jan 8, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 6, 2026 | Sep 1, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2026 | Feb 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2026 | May 19, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2026 | May 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2026 | May 14, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2026 | May 8, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | May 21, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 29, 2026 | May 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2026 | May 8, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 29, 2026 | May 8, 2026 | Approved |
Public Health HEALTH-MH | Apr 29, 2026 | May 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2026 | Jul 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 23, 2026 | Jun 30, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 23, 2026 | Jun 23, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2026 | Jul 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 28, 2026 | Aug 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 29, 2026 | Jul 29, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 30, 2026 | Jul 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2026 | Jul 31, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Jul 31, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Jul 31, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 31, 2026 | Jul 31, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2026 | Aug 6, 2026 | Approved |
Public Health HEALTH-MH | Aug 20, 2026 | Aug 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 21, 2026 | Aug 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 1, 2026 | Sep 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $23,800,000
| Name | Role | License on permit |
|---|---|---|
| Steven Huegli Jensen Architects | Architect | C32013 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025