312 Columbus Av
San Francisco permit 202512101464 · North Beach
(n) lobby/lounge for europa hotel to include: (n) entry vesitbule , (n) toilets, offices, laundry, utilities and storage
- Filed
- Dec 10, 2025
- Issued
- May 4, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 10, 2025 | Dec 10, 2025 | — |
Intake Building Inspection · INTAKE | Dec 10, 2025 | Dec 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 10, 2025 | Dec 10, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 17, 2025 | Dec 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 30, 2025 | Dec 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 20, 2026 | Jan 20, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 26, 2026 | Jan 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 9, 2026 | Mar 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 9, 2026 | Mar 9, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 9, 2026 | Mar 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Mar 13, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2026 | Apr 10, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2026 | Apr 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2026 | Apr 10, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 16, 2026 | Apr 16, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 21, 2026 | Apr 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | Apr 24, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | May 4, 2026 | May 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $573,520
| Name | Role | License on permit |
|---|---|---|
| E Andrew Faust | Architect | C28181 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026