722 19th Av
San Francisco permit 202512111514 · Outer Richmond
Construction of new 2-story detached residential dwelling unit - garage with 1 bedroom apartment above.
- Filed
- Mar 9, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- 14 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2025 | Jan 28, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2026 | Mar 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 10, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Mar 10, 2026 | Mar 31, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2026 | Mar 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 10, 2026 | Mar 12, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2026 | Mar 11, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 10, 2026 | Apr 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2026 | Mar 31, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 10, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Mar 26, 2026 | Apr 3, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2026 | Apr 7, 2026 | Approved |
Address verification Building Inspection · ADDR | Aug 12, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Aug 12, 2026 | Aug 19, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2026 | Aug 25, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2026 | Aug 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 12, 2026 | Aug 13, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2026 | Aug 17, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 12, 2026 | Oct 14, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2026 | Aug 17, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Michael P Ford | Architect | C36260 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2016