345 Spear St #0
San Francisco permit 202512111551 · Financial District/South Beach
1/fl- ti of commerical kitchen at kills plaza. work includes construction of non bearing parititons, finishes, doors, frames and hardware
- Filed
- Dec 11, 2025
- Issued
- Sep 8, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 11, 2025 | Dec 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 17, 2026 | Apr 17, 2026 | Administrative |
Intake Building Inspection · INTAKE | Apr 20, 2026 | Apr 20, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2026 | Apr 21, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 21, 2026 | Apr 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 22, 2026 | Apr 22, 2026 | Issued Comments |
Public health review Public Health · HEALTH | Apr 23, 2026 | Apr 23, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Apr 23, 2026 | Apr 23, 2026 | Issued Comments |
Intake Building Inspection · INTAKE | May 14, 2026 | May 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 14, 2026 | May 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 18, 2026 | May 18, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 18, 2026 | May 18, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | May 26, 2026 | May 26, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 6, 2026 | Jul 6, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 8, 2026 | Jul 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2026 | Jul 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2026 | Jul 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 10, 2026 | Jul 10, 2026 | Approved-Stipulated |
Public health food review Public Health · HEALTH-FD | Jul 10, 2026 | Jul 10, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Aug 21, 2026 | Aug 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2026 | Sep 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Anne Mary Torney Mithun Architects | Architect | C24386 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026