345 Spear St #0
San Francisco permit 202512111591 · Financial District/South Beach
1/fl- scope of work tenant improvement including, non bearing partitions, ceilings, lights, doors, frames, hardware and casework and restroom upgrades for new event space. meps deferred.
- Filed
- Dec 11, 2025
- Issued
- Jul 14, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 13 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 11, 2025 | Dec 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 17, 2026 | Jul 13, 2026 | Administrative |
Intake Building Inspection · INTAKE | Apr 20, 2026 | Apr 20, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 1, 2026 | May 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2026 | May 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 1, 2026 | May 1, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 5, 2026 | Jun 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 5, 2026 | Jun 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2026 | Jun 5, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2026 | Jun 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 7, 2026 | Jul 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2026 | Jul 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $367,000
| Name | Role | License on permit |
|---|---|---|
| Anne Mary Torney Mithun Architects | Architect | C24386 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026