528 Laurel St
San Francisco permit 202512121640 · Presidio Heights
Plaza building-a wing: priority mayor's ed 17-02 - erect a type 1b, 5-story, mixed-use bldg with 62 residential units, bsmnt parking, and commercial tenant spaces. shares plans with plaza b wing under pa # 2025-1211-1587. the plaza building is a single type 1b building with 123 units total.
- Filed
- Feb 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 43 stops across 7 departments
- Comments issued
- 18 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2025 | Jan 5, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 28, 2026 | Feb 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2026 | Feb 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 11, 2026 | Mar 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 11, 2026 | Mar 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 11, 2026 | Feb 24, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2026 | Feb 19, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Feb 11, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2026 | Mar 6, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 11, 2026 | Mar 9, 2026 | Approved |
Public Health HEALTH-AW | Feb 11, 2026 | Feb 25, 2026 | Administrative |
Public Health HEALTH-MH | Feb 11, 2026 | Feb 20, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 11, 2026 | In progress | In Progress |
Urban forestry Public Works · DPW-BUF | Mar 19, 2026 | Mar 19, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 14, 2026 | Aug 25, 2026 | Approved |
Address verification Building Inspection · ADDR | May 14, 2026 | May 26, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 14, 2026 | Jun 11, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 14, 2026 | Jun 4, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 14, 2026 | May 19, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 14, 2026 | May 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 27, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | May 14, 2026 | May 22, 2026 | Approved |
Public Health HEALTH-MH | May 14, 2026 | May 21, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | Jun 29, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2026 | Jul 13, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2026 | Aug 14, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 14, 2026 | Aug 14, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 18, 2026 | Aug 25, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 25, 2026 | Aug 25, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2026 | Sep 14, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 2, 2026 | In progress | — |
Address verification Building Inspection · ADDR | Oct 2, 2026 | Oct 6, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 2, 2026 | Oct 9, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 2, 2026 | Oct 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2026 | Oct 16, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 2, 2026 | Oct 22, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2026 | Oct 20, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 2, 2026 | Oct 8, 2026 | Approved |
Public Health HEALTH-MH | Oct 2, 2026 | Oct 5, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 2, 2026 | Nov 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $31,000,000
| Name | Role | License on permit |
|---|---|---|
| Christian Niel Haegglund Bar Architects | Architect | C18896 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023