2001 20th St
San Francisco permit 202512121701 · Potrero Hill
Repair of damage caused by fire to (e) building and rear deck to comply nov202535024.all interior finishes includuing casewook, tile, wood flooring,plumbing and lighting fixtures shall be replaced inkind. (e) utilities to be replaced in-kind.(e) asphalt shingle roof to be replaced in-kind.
- Filed
- Dec 12, 2025
- Issued
- Mar 23, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 8 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 12, 2025 | Dec 12, 2025 | Administrative |
Building inspector Building Inspection · BID-INSP | Dec 12, 2025 | Dec 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 12, 2025 | Dec 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | Dec 18, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2025 | Dec 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2025 | Dec 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2026 | Mar 23, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $700,840
| Name | Role | License on permit |
|---|---|---|
| Brian T Milford Martinkovic Milford Architects | Architect | C33430 |
| Ashley M Wallace | Authorized agent-others | C38112 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019