3150 Geary Bl #0
San Francisco permit 202512121723 · Presidio Heights
Prop h: ti convert (e) ground level retail space to day care serving children 2-5 years old. occupancy convert from m to e per cbc. (e) bathroom replace w/ 2 new adult bathroom & 2 children bathrooms. one of each will be accessible. new partitions for pre/break room, office, & quiet activity room.
- Filed
- Dec 12, 2025
- Issued
- Apr 30, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 12, 2025 | Dec 12, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 12, 2025 | Feb 9, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2025 | Dec 16, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Dec 17, 2025 | Dec 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Jan 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 22, 2025 | Dec 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 6, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 23, 2026 | Feb 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2026 | Feb 3, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Feb 3, 2026 | Feb 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 4, 2026 | Feb 4, 2026 | Approved |
Public health review Public Health · HEALTH | Feb 9, 2026 | Feb 9, 2026 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2026 | Apr 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $298,294
| Name | Role | License on permit |
|---|---|---|
| Edward Stephan Kaplan Kaplan Architects | Architect | C12668 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025