New horizontal addition, new vertical 4th story addition, add 1/f adu under state program and remodel of existing three stories.

Timeline
Key dates from the city record.
Filed
Jan 24, 2026
Issued
May 11, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
52 stops across 6 departments
Comments issued
12 times, by Permit Center, Building Inspection, Fire Department, Public Utilities

Main permit

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 31, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 23, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 26, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 13, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 27, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 2, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 4, 2026Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Feb 28, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 5, 2026Approved

Permit Processing Center

Building Inspection · PPC

May 7, 2026Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Feb 25, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 13, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 11, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 11, 2026Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Mar 13, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 31, 2026Issued Comments

Zoning review

Planning · CP-ZOC

Apr 13, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 10, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 15, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Apr 13, 2026Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

May 1, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 20, 2026Approved

Street use and mapping

Public Works · DPW-BSM

May 6, 2026Approved-Stipulated

Development fee collection

Building Inspection · DFCU

May 6, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

May 11, 2026Administrative

Addendum 1: Final

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 19, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 20, 2026Administrative

Zoning review

Planning · CP-ZOC

Jun 15, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 30, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 29, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

May 27, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 27, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jun 17, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 4, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 29, 2026Administrative

Fire prevention review

Fire Department · SFFD

May 27, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 4, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 12, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 11, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Aug 13, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Sep 11, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 1, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 1, 2026Approved

Zoning review

Planning · CP-ZOC

Sep 15, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Sep 11, 2026Administrative

Fire prevention review

Fire Department · SFFD

Sep 15, 2026Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Sep 29, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 16, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Sep 17, 2026Approved

Fire prevention review

Fire Department · SFFD

Sep 15, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 5, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Reinstated
Estimated cost
$1,780,479
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gregory K Iboshi

Huang Iboshi Architecture

ArchitectC-27547
Daniel Polivka

Holmes

EngineerC79948
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512151750 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record