2672 Union St
San Francisco permit 202512151750 · Marina
New horizontal addition, new vertical 4th story addition, add 1/f adu under state program and remodel of existing three stories.
- Filed
- Jan 24, 2026
- Issued
- May 11, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 52 stops across 6 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Fire Department, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2025 | Dec 31, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 6, 2026 | Jan 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2026 | Jan 26, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 26, 2026 | Feb 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 26, 2026 | Feb 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 26, 2026 | Feb 2, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2026 | Feb 4, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 26, 2026 | Feb 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2026 | Feb 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 26, 2026 | May 7, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Feb 25, 2026 | Feb 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 10, 2026 | Mar 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 11, 2026 | Mar 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2026 | Mar 11, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 13, 2026 | Mar 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 24, 2026 | Mar 31, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 10, 2026 | Apr 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2026 | Apr 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2026 | Apr 13, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Apr 10, 2026 | May 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2026 | Apr 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 21, 2026 | May 6, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | May 6, 2026 | May 6, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 7, 2026 | May 11, 2026 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 11, 2026 | May 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 20, 2026 | May 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 20, 2026 | Jun 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 20, 2026 | Jun 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 20, 2026 | Jun 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2026 | May 29, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 20, 2026 | May 27, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 20, 2026 | May 27, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 20, 2026 | Jun 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2026 | Jun 4, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 20, 2026 | Sep 29, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 27, 2026 | May 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2026 | Aug 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 10, 2026 | Aug 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2026 | Aug 11, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Aug 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | Sep 11, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 31, 2026 | Sep 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2026 | Sep 1, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 11, 2026 | Sep 15, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 11, 2026 | Sep 11, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 11, 2026 | Sep 15, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 11, 2026 | Sep 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2026 | Sep 16, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2026 | Sep 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2026 | Sep 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2026 | Oct 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $1,780,479
| Name | Role | License on permit |
|---|---|---|
| Gregory K Iboshi Huang Iboshi Architecture | Architect | C-27547 |
| Daniel Polivka Holmes | Engineer | C79948 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2008