167 Bonview St
San Francisco permit 202512161855 · Bernal Heights
1st/f-partial new foundation. excavate 19 cu.yds for slab & footings. convert 386sf of garage to jadu & stairwell.2nd/f-remodel kitchen & dining, relocate bath, add stairwell & steps to rear yard.3rd/f-restructure & raise part of roof to enclose 2 bdrms, 1 bath & 2 decks.front facade- remove...
- Filed
- Jan 14, 2026
- Issued
- Jun 23, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2025 | Jan 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 5, 2026 | Jan 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 15, 2026 | Jan 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Mar 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2026 | Mar 4, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2026 | Feb 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Jan 23, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 15, 2026 | Jan 22, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 15, 2026 | Feb 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 26, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 15, 2026 | Jun 12, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 12, 2026 | Mar 12, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 11, 2026 | May 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 18, 2026 | May 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 18, 2026 | May 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 27, 2026 | Jun 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2026 | May 29, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 27, 2026 | May 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2026 | Jun 3, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jun 2, 2026 | Jun 2, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2026 | Jun 23, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jun 17, 2026 | Jun 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $867,500
| Name | Role | License on permit |
|---|---|---|
| Nate Williams Mosswood Engineering | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023