2100 Jackson St #0
San Francisco permit 202512161861 · Pacific Heights
Renovation of common areas including the addition of a restroom and a lift and construction of a pedestrian connection to existing detached garage. creation of new pedestrian exit from the garage. renoof interiors of units 1b and 1c, including replacement windows.
- Filed
- Jan 13, 2026
- Issued
- Aug 7, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 33 stops across 7 departments
- Comments issued
- 11 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2025 | Dec 31, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 30, 2025 | Dec 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2025 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Mar 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Mar 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Feb 12, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 13, 2026 | Jan 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | May 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 14, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Feb 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Feb 3, 2026 | Approved |
Public Health HEALTH-MH | Jan 13, 2026 | Jan 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | Aug 3, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 3, 2026 | Mar 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2026 | May 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2026 | May 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2026 | May 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 11, 2026 | May 18, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 14, 2026 | May 28, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 10, 2026 | Jun 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 29, 2026 | Jun 30, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 29, 2026 | Jun 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 29, 2026 | Jul 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 2, 2026 | Jul 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2026 | Jul 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2026 | Jul 23, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 23, 2026 | Jul 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 23, 2026 | Jul 27, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 23, 2026 | Jul 31, 2026 | Approved |
Public Health HEALTH-MH | Jul 23, 2026 | Jul 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2026 | Aug 7, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,145,002
| Name | Role | License on permit |
|---|---|---|
| Mark Kevin Hogan Openscope Studio | Architect | C33268 |
| Joe Gulden Imeg | Engineer | 5797 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026