527 Noe St
San Francisco permit 202512161890 · Castro/Upper Market
Expansion of conditioned living space from lower unit 529 to the existing basement to include a new bedroom, bath, and guest room. addition of new interior stairs. renovation of kitchen and bath and add 2nd bath at 1/f. renovate kitchen and bath at upper unit 527.
- Filed
- Feb 12, 2026
- Issued
- Sep 15, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 33 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 16, 2025 | Dec 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 16, 2025 | Dec 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2025 | Dec 16, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 5, 2026 | Jan 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 20, 2026 | Feb 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2026 | Feb 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2026 | Apr 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2026 | Apr 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2026 | Mar 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 13, 2026 | Feb 17, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2026 | Feb 26, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 13, 2026 | Mar 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2026 | Feb 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 13, 2026 | Aug 20, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2026 | Apr 8, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 21, 2026 | Apr 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 14, 2026 | May 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2026 | May 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2026 | May 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2026 | May 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2026 | May 18, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 14, 2026 | Jul 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 14, 2026 | Jun 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2026 | Aug 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2026 | Aug 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2026 | Aug 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Aug 3, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Aug 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2026 | Aug 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2026 | Sep 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $862,235
| Name | Role | License on permit |
|---|---|---|
| Mark Jeffrey Topetcher Topetcher Architectural | Authorized agent-others | C21678 |
| Horon Lee Horon Lee | Engineer | S3818 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024