San Francisco permit 202512161930 · Mission Bay

Commercial or tenant improvementFull plan reviewIssued
Street view · Sep 2026
Google Street View of 350 Kansas St, Sep 2026
Scope of work
As written on the permit application.

Change of occupancy from a-2, m, b, s-1 to only b (tile showroom). tenant improvement permit of (e) two buildings on one lot for a (n) tile showroom as one building. scope of work includes demolition of existing kitchens, restrooms, per plans. new tile display area raised partial floor...

Timeline
Key dates from the city record.
Filed
Jan 9, 2026
Issued
Jun 11, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
6 times, by Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 5, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 9, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 16, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 16, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 5, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jan 14, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 13, 2026Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Jan 21, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jun 5, 2026Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Feb 5, 2026Approved

Building plan review

Building Inspection · BLDG

May 5, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 8, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 12, 2026Approved

Electrical plan review

Building Inspection · MECH-E

May 12, 2026Issued Comments

Building plan review

Building Inspection · BLDG

May 21, 2026Approved

Electrical plan review

Building Inspection · MECH-E

May 20, 2026Approved

Zoning review

Planning · CP-ZOC

Jun 1, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

May 22, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 29, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 11, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,744,929
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Marc Dimalanta

D-Scheme Studio

ArchitectC33350
Jesus Francisco Sierra

Sierra Engineering Group

EngineerS3298
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512161930 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record