350 Kansas St
San Francisco permit 202512161930 · Mission Bay
Change of occupancy from a-2, m, b, s-1 to only b (tile showroom). tenant improvement permit of (e) two buildings on one lot for a (n) tile showroom as one building. scope of work includes demolition of existing kitchens, restrooms, per plans. new tile display area raised partial floor...
- Filed
- Jan 9, 2026
- Issued
- Jun 11, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2025 | Jan 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 6, 2026 | Jan 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2026 | Jan 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Feb 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 9, 2026 | Mar 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Feb 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2026 | Jan 14, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Mar 13, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 9, 2026 | Jun 5, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Feb 5, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2026 | May 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 8, 2026 | May 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2026 | May 12, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 12, 2026 | May 12, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2026 | May 21, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 20, 2026 | May 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 22, 2026 | Jun 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 22, 2026 | May 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 22, 2026 | May 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2026 | May 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2026 | Jun 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,744,929
| Name | Role | License on permit |
|---|---|---|
| Marc Dimalanta D-Scheme Studio | Architect | C33350 |
| Jesus Francisco Sierra Sierra Engineering Group | Engineer | S3298 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026